The projects that go fastest on site are the ones that were slow on paper first.

Every year we have the same conversation in September with someone who wants a shell up before the ground freezes and has not sent us drawings yet. Here is the timeline honestly, so you can work backwards from the date you actually care about.
The real sequence
Take-off and price: a few days once we have usable drawings. Your decision: as long as it takes. Shop drawings: two to four weeks, longer if window selections are still moving. Manufacturing: scheduled after drawings are approved. Delivery: scheduled with you. Assembly: about three days for an average house shell.
So the three days on site sit at the end of something closer to two months of paper. That is not slow — conventional framing needs its own lead time for trusses, engineered lumber and a crew — but it is front-loaded, and front-loading is what catches people.
Order before the foundation, not after
There are two good reasons. First, drawings and manufacturing can run in parallel with sitework, so the panels arrive when the foundation is ready instead of six weeks later. Second, shop drawings sometimes reveal something worth changing — a wall line that wants moving a few inches, an opening better made standard — and those changes are free on paper and expensive in concrete.
What delays a package
In order of frequency: window and door selections not final; foundation dimensions not confirmed as-built; structural questions still open with the engineer; and a decision-maker who is unreachable for two weeks. None of those are our doing and all of them are fixable in advance.
Seasonality
Spring and early summer are the busiest ordering window in this region, which means autumn deliveries fill first. If your target is a shell closed before Thanksgiving, aim to have drawings with us by late summer. Winter assembly itself is not a problem — nothing in the assembly has to dry, and we set panels in the cold routinely — but the paper still takes the time it takes.
If you are already late
Tell us the date you are working to and we will tell you honestly whether it is achievable. A straight no in July is worth more than an optimistic yes that fails in October.
Building in New England?
Send plans, a sketch or a description. We will come back with a panel take-off and a delivered price at no cost. Get a free estimate →
Keep reading
ADUs, shops and small builds around the Monadnock region
The panel system is often thought of as a whole-house decision. Some of the best uses are much smaller.
Financing a low-energy build, and where lenders get stuck
The wall is the easy part. Appraisals and construction draws are where these projects lose momentum.
Why we tell people to halve the HVAC — and what that saves on day one
The upfront equipment saving is the part of the panel budget most people forget to count.
Get a price on your project.
A panel take-off and a delivered price, at no cost — and an honest comparison against building it the usual way.